SP-L2-04 Understanding Consumption versus Productivity.avi

How many feet of ductwork can a crew of three workers install in an hour? What this question is asking is “at what rate can the crew/gang complete one unit of work as measured in hours?” This is the definition of productivity.

Now let’s ask a different question. In an hour, how many feet of ductwork can a crew of three workers install? Or put plainly, “how many resource hours are consumed per each unit installed?” This is the definition of consumption.

WIth this in mind, we can start calculating work hours per unit.